“Jugaani”, “Khirsa”, “Gamarjveba”, “Qistauri” and “Qedi” - 5 new solar power plants built in Kakheti

Georgia’s State Electrosystem is connecting 5 solar power plants with a combined capacity of 10 megawatts to the unified energy grid, marking the first-ever integration of solar energy into the country’s transmission network.

The State Electrosystem has completed installation of modern 6/10 kV voltage cells at five substations in the Kakheti region: Jugaani 110, Khirsa 110, Gamarjveba 110, Qistauri 35, and Qedi 35. This infrastructure upgrade enables the integration of solar power into Georgia’s national grid.

“Against the backdrop of global energy challenges, energy self-sufficiency and energy independence become even more important. Optimal development of renewable energy is one of the Georgian government’s significant priorities”, - said Alexandre Sokhadze, Head of the Energy Policy and Investment Projects Department at the Ministry of Economy.